(a) Construction of
Bait-ul-Zaireen at Bota bagh Hazratbal (3 storeyed):-
Specifications/Cost:-
a.
Plinth area
120’X30’ = 3600 Sft.
90’X30’ = 2700 Sft.
6300 Sft @ Rs 4000/Sft = Rs 2.52 Crore
b.
Sanitary fittings 20 points @ Rs 0.80 lacs =
Rs 16.00 lacs
c.
Electrification
= Rs 15.00 lacs
d.
Furniture.
= Rs 10.00 lacs
e.
Furnishing & appropriate paths.
= Rs 30.00 lacs
Rs 3.23 Crore
Add 2.25%
Rs 37000.00
Rs 3, 23, 73,300
Steel truss Rs 20.00 lacs
Total: -
Rs 3.44 Crore
(b) Construction of
Ladies Mosque (Noor Khana) single storey.
Specifications/Cost:-
i.
RCC footings with RCC columns
j.
Plum concrete 20 plinth with beams.
k.
Column structure with RCC slab.
l.
Deodar wood/kail wood frames and shutters.
m.
Outer & inner walls finished with cement plaster/rubble
dashing.
n.
Kota stone/Marble flooring.
Plinth area:
a.
60’X40’
= 8400Sft @ Rs 1500/Sft
= Rs 126.00 lacs
b.
Electrification.
= Rs 3.00
lacs
c.
Furnishings.
= Rs 3.00 lacs
Total:
-
Rs 1.32 Crore
(c) a.
Construction of single storeyed Dallan on Southern side Gulshan Bagh.
Specification/Cost:-
I.
Plinth area:- 100’X30’ = 3000 Sft @ Rs 1500/Sft Rs 45.00 lacs.
II.
Electrification/Sound system.
Rs 1.50 lacs.
(ci) b.Construction of single storeyed Dallan on Northern side Gulshan Bagh.
Specification/Cost:
i.
Plinth area:- 100’X30’ = 3000 Sft @ Rs
1500/Sft Rs 45.00 lacs
ii.
Electrification/Cost:-
Rs 1.50 lacs
Total = Rs 93.00 lacs
(d) Construction of single storey Media Centre.
Specification/Cost:-
I.
Plinth area:- 40’X25’ = Rs 1000Sft Rs 1500/Sft
Rs 15.00 lacs
II.
Sanitary fittings with Wazoo point.
Rs 0.60 lacs
III.
Electrification.
Rs 0.80 lacs.
IV.
Other items for Displaying of Shrines.
Rs 1.20 lacs
V.
Other items.
Rs
0.26 lacs
Total: -
Rs 17.86 lacs
Approx. Total
Rs
18.00 lacs
(e) Construction of
single storey library with a reading room
a.
Plinth area:- 40’X25’
= 1000Sft @ Rs 1500/Sft = Rs 15.00 lacs
b.
Sanitary fittings – Electrification
= Rs 0.80 lacs
c.
Furnishings + Furniture.
= Rs 0.60 lacs
Add 2.25%
=
Rs 0.36 lacs
Specifications/Cost:-
RCC structure with brick masonry walls and CGI
sheet roofing.
Total: - =
Rs 16.66 lacs
(f) Ornamental fencing
on the shores of Dal Lake.
Specification/Cost:-
I Angle
iron posts and horizontal 50x50x6mm.
II. Plate iron 50mmX6mm section.
iii. 1cmX1cm welded steel mesh 6 ft high above water level.
Iv. Electrification.
Total: -
= Rs 8.00 lacs
(g)
Construction of single storey control room:-
Specifications/Cost:-
a.
Under ground: - RCC
strip foundation.
b.
Above ground: - RCC plinth.
c.
Super structure: - Brick masonry in cement.
d.
Ceiling: -
RCC slab.
e.
Doors/windows: - Deodar/Kail wood.
f.
Finish: -
Cement sand
plaster.
g.
Roofing: -
CGI sheet roofing on wooden trusses.
Plinth area:-
I.
20’X18’ = 360 Sft @ 2000/Sft = Rs 7.20 lacs
II.
Electrification.
= Rs 1.00 lacs
III.
Toilet facility with disposal system.
= Rs 1.50 lacs
Add 2.25%
= Rs 0.22 lacs
Total: -
= Rs 10.00 lacs
(h) Other allied works:-
a), Dev. of
acquired land under expansion programme:-
Rs 50.00 lacs
b). Installation
of central heating system in main Shrine:-
Rs 25.00 lacs.
c), Cosnt. of
two Mehrab gates on the Southern side of Shrine Rs
30.00 lacs
Total Rs 1.05 Crore
Grant Total Rs 9. 09 Crore.